Project Date Project Name
Currently Framing
July 22 Metal building repairs/fixes
July 29 Steel supports for balcony
Aug. 5 Upshur Rural Electric to add/upgrade electrical service.
Aug. 19 Electrician to start
Sept. 2 19 first-floor doors to be delivered.
We are approximately $282,000 of finishing. We are building debt free as the Lord supplies the funds. Praise Him for all He has provided. Follow this link to see a 360 panoramic view of the interior thus far.
Groundbreaking May 16, 2010
A/C units relocated
A/C relocated, upgraded
View the architectural plans in pdf format:
After nearly ten years of negotiations with the State of Texas we have purchased some surplus right-of-way property near Hwy 259. We now have property on which to raise a sign which can be seen from the highway. Below is a pdf of the sign concept we are currently considering.