New Construction Gallery

Image

May 16, 2010



UPDATE 07/18/13

Project Date               Project Name

Currently                      Framing
July 22                         Metal building repairs/fixes
July 29                         Steel supports for balcony
Aug. 5                         Upshur Rural Electric to add/upgrade electrical service.
Aug. 19                       Electrician to start
Sept. 2                        19 first-floor doors to be delivered.

We are approximately $282,000 of finishing.  We are building debt free as the Lord supplies the funds. Praise Him for all He has provided. Follow this link to see a 360 panoramic view of the interior thus far.


Groundbreaking May 16, 2010


A/C units relocated


A/C relocated, upgraded


Dirt work begins

View the architectural plans in pdf format:

First Floor A

First Floor B

First Floor C

First Floor D

First Floor lighting

Fellowship Hall

Fellowship Hall & Kitchen

Fellowship Hall outside

Left & Rear Elevation

Roof Plan

3-D Rendering

After nearly ten years of negotiations with the State of Texas we have purchased some surplus right-of-way property near Hwy 259. We now have property on which to raise a sign which can be seen from the highway. Below is a pdf of the sign concept we are currently considering.

Sign Concept 

Groundbreaking Flyer pdf